Previous
Back to our skills overview

Commissioning

Validating systems performance with commissioning from the outset

Customer issues

1.Validate

system performance from the commissioning stage

2.Ensure

installation quality through QA & QC processes

3.Guarantee

accuracy with pre-startup testing

4.Preserve

integrity during startup operations

5.Maintain

traceability through functional testing

6.Confirm

repeatability via integrated system testing

Commissioning management

Design commissionability reviews

Commissioning plan

Generation of the asset register & "tags"

Factory Witness Testing - FWT

L1: Red Tag - documentation QA & equipment positioned

L 2: Yellow Tag - Installation verification

L3: Green Tag - Start-up

L4: Blue Tag - System level testing

L5: White Tag - Integrated Systems testing (IST)

Electrical Testing & Energisation

  • Safe systems of work and control of energisation. Lock-Out, Tag-Out (LOTO)
  • Pre-energisation design and installation QA/QC
  • Pre-energisation "dead" testing
  • Selectivity and discrimination testing; primary and secondary injection tests.
  • Continuity, polarity and insulation resistance testing of circuit, protection and bonding conductors.
  • Post-energisation testing
  • Volt drop, polarity testing. Earth conductor resistance and earth fault loop impedence testing. Prospective short circuit / fault current measurement
  • Thermal image scanning
  • Functional testing

Mechanical Testing & Energisation

  • Safe systems of work and control of dangerous energy, pressure and heat
  • Pre-startup design and installation QA/QC
  • Filling, flushing and water quality testing
  • Pressure testing - pneumatic (low pressure) and hydraulic testing
  • Ductwork cleanliness checks and pressure testing
  • Fire damper and smoke control system testing
  • BMS / control and monitoring system functional testing

Level 4 System Level Functional Testing & Level 5 IST

  • Development of test scripts and methodologies
  • Planning of heat load testing - air and liquid cooled IT loads
  • Planning of MV Generation, Control & Protection Systems test simulations - Factory and Site Level
  • Planning of load testing and development of procedures for generators, switchgear, UPS, Busbars, PDU's
  • End-to end testing of monitoring and control systems; BMS, EMS, PMS and SCADA.
/api/asset?assetId=/uploads/Datacenter_Rijksuniversiteit_Groningen_1_95afbbd543.jpg